March 2018 - September 2018
Pipework associated with the construction of a new development site at Rothwell
Supply and installation of 573m of DN160 PE gravity fed sewer pipe
Verify location of all existing services
All sewer lines to be tested on completion
Liaise with Unity Water regarding live connections
Construction of 9 x Manholes
All dewatering and groundwater control and disposal of surface water
Compaction testing