BEAUDESERT WTP WEIR REFURBISHMENT
CLIENT: SEQ WATER
October 2018 - January 2019
Repair the damaged sections of gabion rock boxes/mattresses and completely replace the missing sections. The repaired section shall be connected to the existing Gabions and river banks. The top layer shall have a reinforced concrete capping of 30cm. The contractor shall provide IFC & As-built drawings, as a minimum, plans, elevations, connections shall be included.
A geotextile filter shall be placed on the river bed foundation. Total quantity of gabion repair works = 110 cum. Bellrise ensured that there was a continuous Raw Water Supply to the WTP at all times during construction period. Temporary coffer dams where installed using sheet piling to ensure the raw water supply is not affected through the existing infrastructure at all times.