top of page

FEATURE PROJECTS

All services provided by Bellrise Investments are done so with quality and care. Bellrise's projects cover multiple disciplines in the civil construction industry. Check out our selection of projects to give you a taste of what we can achieve.

New 13 Lot Subdivision, including new road, kerb and roundabout. Stormwater management and drainage. Live watermain connection and electrical installation


Additional works completed:
Complete the upgrade to Carsens Avenue Rd at Harrisville from the end of the development from CH 210 to CH340 providing a fully sealed road from Eagle St intersection to Dunns Ave intersection, matching to the portion of works already in progress.
Excavate detention basin outlet to Carsens Avenue. Remove rock, reshape drain, place 6 new 900mm pipes and 2 x 900mm headwalls. Finish the job with concrete stone pitching.

Development Entire.jpg

Site 1: Russian Square Sewer Creek Crossing

Removal of 15.1m of existing DN375 DICL PN35 Tyton Xtreme pipe and 1m3 concrete pier and replace with it with a new 15.1m long OD450 SDR17 PN10 PE100 sewer pipe. The creek crossing replacement pipe is to be concrete encased. The creek bed and banks upstream and downstream of the AC sewer crossing are to be rehabilitated with 300mm thick bed and 230mm thick bank protection using PVC coated reno mattresses.

​

Site 2: Deshon Street Sewer Augmentation 

This project is for the construction of a new DN500 sewer and associated maintenance holes along Deshon Street between Sword Street and Norman Street Woolloongabba. The new sewer is approximately 180m long and shall be predominantly constructed by a trenchless methodology.

field_154120937260398fd4a6efe.jpg

Toowoomba Regional Council, as part of the February 2020 Flood Event, have identified a number of damaged culverts that require replacement. The seven (7) culverts to be removed and replaced by culverts with fish ways (where required) are listed below. The scope of works for this contract involves traffic management, removal of the damaged culverts, installation of the new culverts, end structures, concrete floodways, pavement reconstruction and reinstatement of sealed roads. All works are to comply with standards and specifications set out by the Department of Transport and Main Roads, Toowoomba Regional Council and other relevant government agencies.

Bourke rd (15)_edited_edited.jpg

Bellrise Principal Contractor of Design, Supply and Construct new fire main and water mains for “The Park – Centre for Mental Health”.

The works included:

  • Around 3600m of water mains

  • 2000m of fire mains

  • Between 50mm and 250mm including electrical pumps,

  • Two large water storage holding tanks

  • A pump station building complete with pumps and electrical scada.

IMG_8121.JPG

Installation of 2 x new flow meter pits and the supply, removal and replacement with a new 600mm mag flow meter.

  • Construstion of a pre-cast concrete pit around the DN600 flow meter

  • Construction of a pre-cast concrete pit around the DN750 flow meter

  • Renewal of the 600mm mag flow meter

IMG_4181_edited.jpg

Pipework associated with the construction of a new development site at Rothwell

  • Supply and installation of 573m of DN160 PE gravity fed sewer pipe

  • Verify location of all existing services

  • All sewer lines to be tested on completion

  • Liaise with Unity Water regarding live connections

  • Construction of 9 x Manholes

  • All dewatering and groundwater control and disposal of surface water

  • Compaction testing

Rothwell Caboolture_edited.jpg

©2019 by Bellrise Investments.

bottom of page