FERNVALE SEWERAGE SCHEME UPGRADE

CLIENT: BROADSPECTRUM
2018 - 2019

Pump Station
Construction of new 4m dia, 8m deep sewerage pump station at Fernvale including; 2.4 dia concrete plastic lined emergency storage tank, all associated MHs and structures PE lined, asphalt access road, overflow
pipeline and portable water pipeline.

​

Rising Main & Recycled Water Main
Construction of a new 6.8km DN280 HDPE PE100 PN16 Rising Main from the new Fernvale SPS to the new Lowood STP. Construction of a new 2.5km DN180 HDPE PE100 PN16 Recycled Water Pipeline from the new Lowood STP toward Fernvale. Construction of all associated MH’s, valve chambers and air valve.