WOOGAROO TRUNK SEWER MAIN -Â Â Â Â TRENCHED PIPEWORKS
CLIENT: THIESS
June 2011 - November 2012
The Woogaroo Trunk Sewer Main contract included the supply of plant & labour, supervision, equipment, materials, investigations and permits required for the trenched pipe works including:
Compile safety plans, method statements and ITPs to manage the works.
Survey set out
Excavate, lay, backfill and test 2600m of 1200mm RC pipe ranging in depth from 3m to 9.5m
Construct 40 instu manhole structures including PE liners ranging in size from 1500mm to 2100mm dia in accordance with the drawings and specifications
Construct bored pile and pilecaps for aerial crossings including installation of 1200mm MSCL pipe and headstocks
Excavation and removal of 3600m³ of rock
Design and supply shoring & dewatering of the works
Welding and testing of plastic liners in concrete pipes & manhole units for the full length of the work
Vacuum testing of completed works
Compile and submission of `As Built` documentation